Our customer that produces thick wall plastic piping was struggling with cycle times when molding 90° pipe elbows. Their cycle time was 256 seconds.
FEA analyis
FEA analisys was carried out, predicting a massive cycle time reduction to 125 seconds.
FEA analyis
Based on big potential savings customer decided to replace its current core with conformally cooled iTherm® Core.
Current convetionally made Core
iTherm® Core with conformal cooling channels
Tool scheme with iTherm® Core
Current convetionally made Core
iTherm® Core with conformal cooling channels
Cycle time reduced by 54,7%, from 256s to 116s